Friday, July 16, 2010

i-city MSC: No 1 Technology city in Malaysia









Project Manager : i- Berhad

BOARD OF DIRECTORS

Chairman:
Y. Bhg. Tan Sri Dato’ Sri Hamad Kama Piah Bin Che Othman

Deputy Executive Chairman
Y. Bhg. Datuk Lim Kim Hong

Executive Director
Y. Bhg. Datin Tey Siew Thuan

Chief Executive Officer/Executive Director
Mr. Eu Hong Chew

Independent Non-Executive Director
Y. Bhg. Datuk Abu Hassan Bin Kendut

Non-Executive Director
Madam Ong Poh Ling


Scope of the project:

1) To make i -city into both knowledge hub as well as tourism spot in Shah Alam

2) The tourism components of i-City comprises the Shopping Mall, CityWalk, Animation Studios, the Riverfront and the City of Digital Lights.

2) To bring the vision nearer to reality like the launching of the City of Digital Lights and the Technopreneur Campus programme. In the mean time, i-City has been designated as its first and flagship campus.









3) Under the City of Digital Lights programme ( launched in Dec 2009), the park and streets of i-City would be decorated with LED lights themed to reflect the festivities of the various communities.







4) In March 2010, this company entered into a strategic alliance with the Selangor State Economic Development Corporation (PKNS) and Plug and PlayTech Centre to set up the ecosystem required for a successful incubation programme.

5) The State also announced that it has budgeted an initial RM50 million to invest in these technology companies. The State further stated that it would be accelerating the construction of the direct access from the Federal Highway into i-City.


MASTER PLAN AND THE TIME FRAME


Planned MSC Malaysia Cybercentres
Number of Floors
Total Floor Space (SQFT)
Target Completion
Phase 1A - CityPark: Block A B C D E F
156
301786
Jun 2008
Phase 1B - CityPoint: Block J K L
110
158938
Apr 2009
Phase 1C - CityWalk & Block R
200
>1000000
Dec 2010
Phase 1D - Innovation Centre
7
48401
Dec 2010
Phase 1E - Block M N P Q
30
284114
Dec 2012
Phase 2A - Technology Centre
70
653880
Dec 2013
Phase 2B - Corporate Tower P2
123
778644
Dec 2015
Phase 2C - Corporate Tower P1
270
1297118
Dec 2015




2010 oUTLOOK

The i- Berhad is planning for a tower development on top of the Car Park Block to serve both the SOHO market as well as the Incubation Centre.

they are also planning the development of the second Tier 4 data centre block.

http://i-city.my/
resources: i- Berhad 2009 annual report


2 comments:

  1. hye afiqah,
    as we all know, i city is the most project in Malaysia that shows Malaysia nowadays look forwards through globalization.
    Tq.
    Ahmad Afifi Othman

    ReplyDelete
  2. yes...towards vision 2020..(",)

    ReplyDelete